Float and Critical Path

If the float is zero, then you can say the activity is on a critical path. So you can conclude the non zero float activity will be in non-critical path

You can calculate float by either:

  • Late Finish (LF) – Early Finish (EF) … or
  • Late Start (LS) – Early Start (ES)